We are pleased to share a few examples of the Epsilon design-build and design-build-install solutions over the past several years. This is a representative sample and we are happy to provide examples that may be more relevant to your site or industry.

Case Studies

From Abandoned Retail to Leading Medical Center

Challenge NYU Langone Health had a goal – and a challenge.  The organization wanted to build a new medical center in the Garden City community of Long Island, NY.  However, land was hard to come by in this high-density region, and the typical cost escalations…
Case Studies

325 Main Super Skid Case Study

Challenge Boston Properties was developing a new 18-story high-rise building to serve technology and life science tenants in the rapidly evolving innovation hub of Kendall Square in Cambridge, Massachusetts.  They faced a very tight urban site, an aggressive schedule, and a labor force that was…
Case Studies

From Factory to Field: Educational Facility

Challenge: Renovations at a Texas elementary school did not allow room inside the building for new boilers and chilled water pumps. Solution: Epsilon designed and fabricated a standalone modular hot water boiler and chilled water distribution pump package with two 2,000 MBH hot water boilers…
Case Studies

18-Story Office Building Mechanical System

Challenge: An 18-story office building with more than 1.12 million square feet needed a full mechanical system renovation, with minimal disruption to tenants and adjacent properties. Solution: Integration partner HTS New York engaged Epsilon based on our past successes delivering modular central plant solutions. Together,…
Case Studies

Pharmaceutical Manufacturing Central Utility Plant

Challenge: Boehringer Ingelheim (BI) – a leading pharmaceutical company – was planning to construct a new central chilled water plant to replace an underperforming existing system.  The project presented substantial technical challenges:  the process system required a steady 27oF entering water temperature while accommodating drastic…
Case Studies

Medical Center Central Utility Plant

Challenge: Holy Cross Health planned to construct a new hospital facility that would include a full-service emergency department, maternity ward, surgical services, and psychiatric care – along with an adjacent medical office building.  The 6-story, 237,000-square-foot, 78-bed facility would be the first new hospital in…
Case Studies

Telecommunications Central Utility Plant and Data Center

Challenge A leading global telecommunications company had plans to build new office space and data center in the heart of its’ existing southern California corporate campus.  These plans required an additional 2,800-tons of central cooling plant capacity, along with approximately 2MW of additional data center…
Case Studies

General Motors Paint Shop Cooling Plant

GM Cooling Project Wentzville, MO Challenge The General Motors facility in Wentzville, MO had undergone multiple building and process expansions over many years.  As a result, the site was left short on process cooling, threatening paint shop production in the hot summer conditions.  And given…